Fin – hard rock cafe problem

Get Custom Essay on Fin – hard rock cafe problem

Let Our Team of Pofessional Writers Take Care of Your Paper.

At the Hard Rock Cafe, like many organizations, project management is a key planning tool. With Hard Rock’s constant growth in hotels and cafes, remodeling of existing cafes, scheduling for Hard Rock Live concert and event venues, and planning the annual Rockfest, managers rely on project management techniques and software to maintain schedule and budget performance.
“Without Microsoft Project,” says Hard Rock Vice-President Chris Tomasso, “there is no way to keep so many people on the same page.” Tomasso is in charge of the Rockfest event, which is attended by well over 100,000 enthusiastic fans. The challenge is pulling it off within a tight 9-month planning horizon. As the event approaches, Tomasso devotes greater energy to its activities. For the first 3 months, Tomasso updates his MS Project charts monthly. Then at the 6-month mark, he updates his progress weekly. At the 9- month mark, he checks and corrects his schedule twice a week.
Early in the project management process, Tomasso identifies 10 major tasks (called level 2 activities in a work breakdown structure, or WBS):talent booking, ticketing, marketing/PR, online promotion, television, show production, travel, sponsorships, operations, and merchandising. Using a WBS, each of these is further divided into a series of subtasks. The following table identifies 26 of the major activities and subactivities, their immediate predecessors, and time estimates. Tomasso enters all of these into the MS Project software. Tomasso alters the MS Project document and the time line as the project progresses. “It’s okay to change it as long as you keep on track,” he states.
Activity Description Predecessor Normal Time (weeks) Normal Cost Crash Time (weeks) Crash Cost
A Finalize site and building contracts — 7 $7,500 4 $11,500
B Select local printer A 3 $500 2 $800
C Hire production manager A 3 $1,200 2 $1,700
D Design promotional Web site B 5 $6,000 3 $9,000
E Set TV deal D 6 $4,000 4 $6,500
F Hire director E 4 $1,200 3 $1,700
G Plan for TV camera placement F 2 $500 2 $500
H Target headline entertainers B 4 $2,000 3 $3,500
I Target support entertainers H 4 $2,000 3 $3,500
J Travel accommodations for talent I 10 $9,000 7 $16,000
K Set venue capacity C 2 $300 1 $400
L Ticketmaster contract D 3 $1,400 2 $1,900
M On-site ticketing L 8 $7,000 6 $11,000
N Sound and staging C 6 $9,000 5 $12,000
O Passes and stage credentials G 7 $4,000 5 $5,800
P Travel accommodations for staff B 20 $15,000 15 $23,000
Q Hire sponsor coordinator B 4 $600 3 $800
R Finalize sponsors Q 4 $1,000 3 $1,400
S Define/place signage for sponsors R 3 $3,000 2 $4,200
T Hire operations manager A 4 $1,200 2 $1,800
U Develop site plan T 6 $6,000 5 $8,500
V Hire security director T 7 $1,500 5 $3,000
W Set police/fire security plan V 4 $1,000 3 $1,600
X Power, plumbing, AC, toilet services U 8 $4,000 6 $7,000
Y Secure merchandise deals B 6 $6,000 3 $7,500
Z Online merchandise sales Y 6 $5,000 4 $7,500
The day of the rock concert itself is not the end of the project planning. “It’s nothing but surprises. A band not being able to get to the venue because of traffic jams is a surprise, but an ‘anticipated’ surprise. We had a helicopter on stand-by ready to fly the band in,” says Tomasso.
On completion of Rockfest in July, Tomasso and his team have a 3-month reprieve before starting the project planning process again.
Source: Professor Barry Render, Jay Heizer and Beverly Amer.
Please turn in a paper of one to two pages (page counting does not include cover and reference list) discussing the following questions:

1. Identify the critical path and its activities for Rockfest. How long does the project take (what is the duration time)?
2. which activities have a slack time of 8 weeks or more ?
3. Identify some major challenges a project manager faces in events such as this one.
4. why is a work breakdown structure useful in a project such as this ? take the 26 activities and break them into what you think should be level-2, level-3 and level-4 tasks.

Calculate the price for this paper
Pages (550 words)
Approximate price: -

Try it now!

Calculate the price for this paper

We'll send you the first draft for approval by at
Total price:
$0.00

How it works?

Follow these simple steps to get your paper done

Place your order

Fill in the order form and provide all details of your assignment.

Proceed with the payment

Choose the payment system that suits you most.

Receive the final file

Once your paper is ready, we will email it to you.

Our Services

Best Quality Essays has stood as the world’s leading custom essay writing services providers. Once you enter all the details in the order form under the place order button, the rest is up to us.

Essays

Essay Writing Services

At Best Quality Essays, we prioritize on all aspects that bring about a good grade such as impeccable grammar, proper structure, zero-plagiarism and conformance to guidelines. Our experienced team of writers will help you completed your essays and other assignments.

Admissions

Admission and Business Papers

Be assured that you’ll definitely get accepted to the Master’s level program at any university once you enter all the details in the order form. We won’t leave you here; we will also help you secure a good position in your aspired workplace by creating an outstanding resume or portfolio once you place an order.

Editing

Editing and Proofreading

Our skilled editing and writing team will help you restructure you paper, paraphrase, correct grammar and replace plagiarized sections on your paper just on time. The service is geared toward eliminating any mistakes and rather enhancing better quality.

Coursework

Technical papers

We have writers in almost all fields including the most technical fields. You don’t have to worry about the complexity of your paper. Simply enter as much details as possible in the place order section.